Oso landslide, river change and State Route 530 recovery milestones

Sources checked

Landslide and recoveryOso river change and highway recovery in 2014
  1. 22 March 2014
    Landslide crossed the valley

    The slide near Oso travelled almost two kilometres. Its deposit crossed State Route 530 and blocked the North Fork Stillaguamish River. · Landslide Source 1

  2. 23 March 2014
    River overtopped the deposit

    Water began flowing over a low part of the deposit within about 25 hours of the landslide. · River Source 2

  3. 24 March 2014
    Aerial surveys measured the site

    The USGS assessment lists lidar at one-metre horizontal resolution and aerial imagery at 0.3-metre resolution for this date. · Survey Source 1

  4. 26 March 2014
    Crews opened an alternate access route

    State and county crews cleared the Mountain Loop Highway as work also connected State Route 530 with a utility road for responders. · Road and access Source 3

  5. Early April 2014
    Pilot channel excavated

    County and cooperating agencies cut a pilot channel in the eastern part of the deposit to speed drainage during the search effort. · River and response Source 1

  6. 25 April 2014
    Piloted public access contracted

    Washington State Department of Transportation contracted work to guide public traffic on a separate utility access road. · Road and access Source 3

Show 7 more dates
  1. May 2014
    River channel re-established through the deposit

    A USGS study reports a deeply inset channel 20 to 40 metres wide through the deposit by May. · River Source 2

  2. 30 May 2014
    Highway clearing completed

    The county project account records about 127,000 tons of debris moved during the State Route 530 clearing project. · Road and access Source 3

  3. 31 May 2014
    Highway reopened to piloted traffic

    State Route 530 reopened through the area to one-way piloted traffic. · Road and access Source 3

  4. 1 June 2014
    Standing pool receded at lower flows

    USGS reports that by this date no standing pool remained at river flows below about 57 cubic metres per second. · River Source 1

  5. July 2014
    Water surface approached its earlier profile

    USGS found the channel water surface about one metre above its pre-landslide profile. · River Source 2

  6. 22 September 2014
    Highway reconstruction substantially complete

    The state recorded substantial completion of the emergency roadway reconstruction project. · Road and access Source 3

  7. First 18 months
    Sediment moved downstream

    USGS estimated 820,000 metric tonnes of sediment eroded from the deposit into the river over the first 18 months. · River Source 2

Choose a milestone to trace the first day, the river’s changing channel or the return of road access.

Source 1 Source 2 Source 3

Oso landslide, river change and State Route 530 recovery milestones

Dates and measurements come from USGS field investigations and the state and county project record. River sediment estimates and road-clearing totals describe different material and use the units reported by each source.

13 records
Source
22 March 2014Landslide crossed the valleyThe slide near Oso travelled almost two kilometres. Its deposit crossed State Route 530 and blocked the North Fork Stillaguamish River.LandslideSource 1
23 March 2014River overtopped the depositWater began flowing over a low part of the deposit within about 25 hours of the landslide.RiverSource 2
24 March 2014Aerial surveys measured the siteThe USGS assessment lists lidar at one-metre horizontal resolution and aerial imagery at 0.3-metre resolution for this date.SurveySource 1
26 March 2014Crews opened an alternate access routeState and county crews cleared the Mountain Loop Highway as work also connected State Route 530 with a utility road for responders.Road and accessSource 3
Early April 2014Pilot channel excavatedCounty and cooperating agencies cut a pilot channel in the eastern part of the deposit to speed drainage during the search effort.River and responseSource 1
25 April 2014Piloted public access contractedWashington State Department of Transportation contracted work to guide public traffic on a separate utility access road.Road and accessSource 3
May 2014River channel re-established through the depositA USGS study reports a deeply inset channel 20 to 40 metres wide through the deposit by May.RiverSource 2
30 May 2014Highway clearing completedThe county project account records about 127,000 tons of debris moved during the State Route 530 clearing project.Road and accessSource 3
31 May 2014Highway reopened to piloted trafficState Route 530 reopened through the area to one-way piloted traffic.Road and accessSource 3
1 June 2014Standing pool receded at lower flowsUSGS reports that by this date no standing pool remained at river flows below about 57 cubic metres per second.RiverSource 1
July 2014Water surface approached its earlier profileUSGS found the channel water surface about one metre above its pre-landslide profile.RiverSource 2
22 September 2014Highway reconstruction substantially completeThe state recorded substantial completion of the emergency roadway reconstruction project.Road and accessSource 3
First 18 monthsSediment moved downstreamUSGS estimated 820,000 metric tonnes of sediment eroded from the deposit into the river over the first 18 months.RiverSource 2