Brisbane flood gauge and infrastructure recovery timeline

Sources checked

From the river crest to completed transport linksBrisbane flood gauge and infrastructure recovery timeline
  1. 12 January 2011
    The Bremer River at Ipswich peaked at 19.4 m.

    Source 2

  2. 13 January 2011
    The Brisbane City gauge peaked at 4.46 m.

    Source 2

  3. 26 February 2011
    Queensland secured replacement funding for the two transport projects.

    Source 3

  4. September 2014
    The replacement Riverwalk was completed.

    Source 3

  5. 2015
    Reconstruction of seven ferry terminals was completed.

    Source 3

The first records track water level. The later records show funding and construction of two damaged transport links.

Source 1 Source 2 Source 3

Brisbane flood gauge and infrastructure recovery timeline

Heights are local gauge readings, measured from each gauge’s own datum. The Brisbane City and Ipswich numbers refer to different sites. Time of day is local. The recovery entries are selected milestones for the Riverwalk and ferry terminals.

10 records
Source
11 January 2011Brisbane City gauge reaches minor flood rangeBegan the 11 to 14 January period above the 1.7 m minor thresholdSource 1
12 January 2011Brisbane City gauge above major flood thresholdThe threshold is 3.5 m at this gaugeSource 1
12 January 2011Bremer River peak at Ipswich19.4 m on the Ipswich gaugeSource 2
13 January 2011Brisbane River crest at Brisbane City4.46 m at about 3:00am local timeSource 2
14 January 2011Last date in the above-minor interval at Brisbane CityThe Bureau reports an 11 to 14 January interval above minor levelSource 1
17 January 2011Queensland flood inquiry announcedThe state announced an inquiry after widespread floodingSource 2
26 February 2011Funding secured for Riverwalk and terminal replacementUp to AUD 145 million from the joint disaster relief packageSource 3
July 2013Permanent Riverwalk construction beganReplacement of the original floating walkwaySource 3
September 2014Replacement Riverwalk completedReopened the walking and cycling connection between New Farm and the central citySource 3
2015Reconstruction of seven ferry terminals completedBrisbane City Council completed the worksSource 3