Navigational access and restoration milestones at Baltimore in 2024
Sources checked
- 26 March 2024Federal channel blocked
The collapse of the Francis Scott Key Bridge blocks the main shipping channel. Source 1
- 2 April 2024Temporary alternate channel
The first of three temporary alternate channels opens to shallow-draft traffic. Source 1
- 25 April 2024Limited Access Channel opens
A 300-foot-wide passage at 35 feet deep opens through the area. Source 2
- 9 May 2024Recreational transit allowed
The Unified Command permits recreational vessels to pass through the response safety zone. Source 1
- 20 to 21 May 2024Deep-draft access returns
A passage 400 feet wide and 50 feet deep becomes available for deep-draft commercial vessels. Source 3
- 4 June 2024Last major truss removed
The Corps records removal of the last major steel truss from the federal channel. Source 1
Show 1 more dates
- 10 June 2024Full federal dimensions restored
A survey confirms restoration of the 700-foot-wide, 50-foot-deep navigation channel. Source 1
Choose a date to jump to the dimensions and official record.
Navigational access and restoration milestones at Baltimore in 2024
Channel dimensions are the operational figures published by the Corps. The events track waterway access and clearance at the port.
| Source | |||
|---|---|---|---|
| 26 March 2024 | Federal channel blocked | The collapse of the Francis Scott Key Bridge blocks the main shipping channel. | Source 1 |
| 2 April 2024 | Temporary alternate channel | The first of three temporary alternate channels opens to shallow-draft traffic. | Source 1 |
| 25 April 2024 | Limited Access Channel opens | A 300-foot-wide passage at 35 feet deep opens through the area. | Source 2 |
| 9 May 2024 | Recreational transit allowed | The Unified Command permits recreational vessels to pass through the response safety zone. | Source 1 |
| 20 to 21 May 2024 | Deep-draft access returns | A passage 400 feet wide and 50 feet deep becomes available for deep-draft commercial vessels. | Source 3 |
| 4 June 2024 | Last major truss removed | The Corps records removal of the last major steel truss from the federal channel. | Source 1 |
| 10 June 2024 | Full federal dimensions restored | A survey confirms restoration of the 700-foot-wide, 50-foot-deep navigation channel. | Source 1 |